Ford Manchester – Full Mechanical, Electrical, Interior & AV/IT Fit-Out
The project comprised a high-spec Category B office fit-out within an existing CAT-A space, transforming a 17,000 sq ft floor plate into a modern, comfortable workspace that meets Ford’s corporate standards. Works included full MEP installation with coordinated HVAC design and integration, staged commissioning for seamless delivery, and structural reinforcement to ensure stability.
Acoustic enhancements were introduced for improved sound control, alongside advanced AV/IT systems for connectivity. Premium interior finishes, bespoke joinery, signage, and glazing completed the aesthetic, while quality was assured through a rigorous snagging and certification process, all delivered under disciplined project management and site control protocols.
Solution
MGL Projects acted as the Main Contractor, managing site delivery and maintaining close collaboration with the Ford project team and CBRE.
A dedicated delivery team was deployed, supported by MGL’s Project Execution Tracker, weekly reporting, and disciplined subcontractor management to coordinate MEP, structural, and AV/IT workstreams.
Detailed MEP coordination drawings, sequenced works, and staged commissioning helped minimise on-site clashes, while a structured snagging and certification programme ensured all systems were tested, certified, and handed over on schedule, meeting quality expectations and aligned approvals
What did MGL Projects deliver for Ford in Manchester?
MGL Projects was main contractor for a high-spec Category B office fit-out within an existing CAT A space at First Street, Manchester, turning a 17,000 sq ft floor plate into a modern workspace that meets Ford's corporate standards.
What was included in the Ford fit-out?
Full MEP installation with coordinated HVAC, staged commissioning, structural reinforcement, acoustic enhancements, AV/IT systems, premium interior finishes, bespoke joinery, signage and glazing.
How did MGL manage delivery with Ford and CBRE?
MGL worked closely with the Ford project team and CBRE, using a dedicated delivery team, its Project Execution Tracker and weekly reporting. Detailed MEP coordination drawings and sequenced works kept clashes down, and a structured snagging and certification programme saw every system tested, certified and handed over on schedule.
Services
Delivering seamless design, bespoke joinery, and coordinated mechanical solutions to enhance functionality, quality, and project efficiency.
01
Design and Build
Deliver bespoke designs that elevate brand standards, ensuring functionality, aesthetics, and alignment with client vision.
02
Bespoke Joinery
Managing the delivery and installation of bespoke joinery ensuring quality, precision, and timely completion in line with project specifications.
03
Mechanical Coordination
Oversee the integration of mechanical systems (HVAC, plumbing, fire safety) within the project design and construction phases, ensuring spatial compatibility, regulatory compliance, and efficient operation without impacting aesthetics or timelines.